Modelling guide

Scrap, yield and OEE

An inspection rejects a share of units for good (a leak test, a final check), and the factory must still deliver the good units its customers ask for.

Built in A field or setting does it directly.

When

You want good output, yield and each station's OEE.

How

On the product's operations:

  • Set scrap_probability (0.1) on the step that rejects units (Product table → Scrap). As that step finishes, that share of units is scrapped: the unit leaves at that station, is counted as scrapped and never as output.
  • Each scrapped unit is replaced at once by a new unit of the same product for the same demand, so orders and arrivals are still met in good units. Its varied dimensions are drawn again.
  • Build layout sizes the scrapping step and every step before it for the extra units, 1 / (1 − s) for each scrap point s at or after it; the steps after it see only good units.
  • The results give summary.scrapped, summary.yield (good / (good + scrapped)) and, per station, scrapped and oee: availability (not stopped for breakdowns, maintenance or its crew) × performance (working while available; waiting for units, blocked and short of parts count against it) × quality (finished and not scrapped there).
  • A share on a part a feeder makes works the same way: the part is made again for the same parent, and the feeder is sized for it.
  • At a breakdown: a machine's failure_scrap_probability (Hardware → Scrapped at a breakdown) scraps that share of the units on it when it breaks down (with reliability_mode on).
  • After a wait: an operation with max_wait_s/max_wait_until and max_wait_scrap: true (Product table → Over max wait: Scrapped) scraps a unit still queued for the later step when the limit runs out (work centres and job shops).

Scrapped units go to a scrap bin beside the station and can come back as raw material: see Scrap bins and recycling.

Check

Pumps are assembled, sealed and leak tested; the test rejects 10% for good. Pumps are ordered every 10 minutes on average for 40 hours. About 25 pumps are scrapped and replaced, every order is still met, and assembly and sealing get a second station for the extra pumps while the test, which does them at 240 s, keeps one.